Reyes Group Ltd., as part of the Joint Venture Agreement, was directly responsible for the
General Supervision of the following portion of the contract totaling $7.2 million over a two
and one half year period.
Please note: Reyes Group Ltd. also self-performed portions of the work:
- Crew Facility Building
- Signal and MOW Storage Building
- Mechanical Storage Building
- Generator/Compressor Building
- LaFox Commuter Station which includes: Warming House, South Building,
Ramps and Tunnels
Scope of Work Includes:
- Excavation
- Waterline
- Sewer
- C-I-P Concrete
- Doors and Frames
- Rebar Installation
- Hollow Core Precast
- Painting
- Electrical
- Masonry
- Overhead Door
- Interior Ductbank Encasement
- Flatwork
- Landscape
- Metal Grillages
- Fence
- Asphalt Paving
- Finish Hardware
- Signs
- Roofing